Daily summary The day's site activity focused on Skim coat work, Plastering work, and Lantai Granit across 18 work areas, supported by Work item needs review, Concrete casting work, and Dinding Granit Kamar mandi.
Work by area Work area 01 · page 1 of 2 Unit A facade
Standard area
Unit A facade 4 entries on this page Plastering work Skim coat work
Bambang Fery Hosnan Miskat Topik Yayan Zaeni
Skim coat work Bambang Unit A facade
Plastering work Fery Unit A facade
Skim coat work Hosnan Unit A facade
Skim coat work Miskat Unit A facade
Work by area Work area 01 · page 2 of 2 Unit A facade
Standard area
Unit A facade 3 entries on this page Plastering work Topik Unit A facade
Work by area Work area 02 · page 1 of 2 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Plastering work Skim coat work
Al Joko Mujiono Ridho Soleh Wahyu
Skim coat work Al Unit A lobi
Work by area Work area 02 · page 2 of 2 Unit A lobi
Standard area
Unit A lobi 2 entries on this page Skim coat work Soleh Unit A lobi
Work by area Work area 03 · page 1 of 2 Unit A
Standard area
Unit A 4 entries on this page Lightweight brick installation Work item needs review
Fatta Fian Riswan Subawi Wafi
Work item needs review Fatta Unit A
Work by area Work area 03 · page 2 of 2 Unit A
Standard area
Unit A 1 entry on this page Work item needs review Wafi Unit A
Work by area Work area 04 Unit C basement
Standard area
Unit C basement 4 entries on this page Dinding Granit Kamar mandi Structural column work Work item needs review
Ari Huri Imron Toni
Dinding Granit Kamar mandi Ari Unit C basement
Work by area Work area 05 Unit B Third Floor
Standard area
Unit B Third Floor 3 entries on this page Lantai Granit Plastering work
Adip Dofir Tormudi
Lantai Granit Adip Unit B Third Floor
Work by area Work area 06 Kolam pagar air mancur
Standard area
Kolam pagar air mancur 2 entries on this page Concrete casting work
Dulbari Wahid
Concrete casting work Dulbari Kolam pagar air mancur
Work by area Work area 07 Unit A Third Floor
Standard area
Unit A Third Floor 2 entries on this page Plastering work
Halim Naim
Plastering work Halim Unit A Third Floor
Work by area Work area 08 Unit B facade
Standard area
Unit B facade 2 entries on this page Plastering work
Akseh Ropek
Plastering work Akseh Unit B facade
Work by area Work area 09 Unit B Second Floor
Standard area
Unit B Second Floor 2 entries on this page Lantai Granit Skim coat work
Afis Dhoni
Lantai Granit Afis Unit B Second Floor
Work by area Work area 10 Unit C Room 12
Standard area
Unit C Room 12 2 entries on this page Lantai Granit
Andri Sam
Lantai Granit Andri Unit C Room 12
Work by area Work area 11 Unit C Third Floor
Standard area
Unit C Third Floor 2 entries on this page Lantai Granit
Bais rizal
Lantai Granit Bais Unit C Third Floor
Work by area Work area 12 Area not filled
Standard area
Area not filled 1 entry on this page Belanja / Logistik Site
Faisal
Belanja / Logistik Site Faisal Area not filled
Work by area Work area 13 Unit B belakang
Standard area
Unit B belakang 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Unit B belakang
Work by area Work area 14 Unit B tangga utama
Standard area
Unit B tangga utama 1 entry on this page Skim coat work
Gazali
Skim coat work Gazali Unit B tangga utama
Work by area Work area 15 Unit C Room 14
Standard area
Unit C Room 14 1 entry on this page Work item needs review
Pawait
Work item needs review Pawait Unit C Room 14
Work by area Work area 16 Unit C Room 15
Standard area
Unit C Room 15 1 entry on this page Tile installation
Hanan
Tile installation Hanan Unit C Room 15
Work by area Work area 17 Unit C Room 22
Standard area
Unit C Room 22 1 entry on this page Work item needs review
Hoirul
Work item needs review Hoirul Unit C Room 22
Work by area Work area 18 Unit C Room 23
Standard area
Unit C Room 23 1 entry on this page Work item needs review
suarji
Work item needs review suarji Unit C Room 23
Standard check and completeness Work item does not match standard naming yet 7 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 1 entry Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 1 entry The site input does not mention a work area, so it is not used as a final progress conclusion by area.