Daily summary The day's site activity focused on Skim coat work, Plastering work, and Work item needs review across 17 work areas, supported by Lantai Granit, Pembersihan Area Kerja, and Concrete casting work.
Work by area Work area 01 · page 1 of 3 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Pembersihan Area Kerja Plastering work Skim coat work
Al Joko Mujiono Ridho Soleh Subawi Topik Wahyu Zaeni
Skim coat work Al Unit A lobi
Skim coat work Joko Unit A lobi
Plastering work Mujiono Unit A lobi
Skim coat work Ridho Unit A lobi
Work by area Work area 01 · page 2 of 3 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Skim coat work Soleh Unit A lobi
Work by area Work area 01 · page 3 of 3 Unit A lobi
Standard area
Unit A lobi 1 entry on this page Plastering work Zaeni Unit A lobi
Work by area Work area 02 · page 1 of 2 Unit C basement
Standard area
Unit C basement 4 entries on this page Concrete casting work Lantai Granit Work item needs review
Ari Huri Imron Sam Toni Wahid
Lantai Granit Ari Unit C basement
Work by area Work area 02 · page 2 of 2 Unit C basement
Standard area
Unit C basement 2 entries on this page Work item needs review Toni Unit C basement
Work by area Work area 03 · page 1 of 2 Unit A facade
Standard area
Unit A facade 4 entries on this page Skim coat work
Bambang Fery Hosnan Miskat Yayan
Skim coat work Bambang Unit A facade
Work by area Work area 03 · page 2 of 2 Unit A facade
Standard area
Unit A facade 1 entry on this page Skim coat work Yayan Unit A facade
Work by area Work area 04 · page 1 of 2 Unit B facade
Standard area
Unit B facade 4 entries on this page Plastering work Skim coat work
Akseh Dhoni Halim Naim Ropek
Plastering work Akseh Unit B facade
Work by area Work area 04 · page 2 of 2 Unit B facade
Standard area
Unit B facade 1 entry on this page Plastering work Ropek Unit B facade
Work by area Work area 05 Unit A
Standard area
Unit A 3 entries on this page Work item needs review
Fatta Fian Wafi
Work item needs review Fatta Unit A
Work by area Work area 06 Unit B Third Floor
Standard area
Unit B Third Floor 3 entries on this page Lantai Granit Plastering work
Adip Dofir Tormudi
Lantai Granit Adip Unit B Third Floor
Work by area Work area 07 Unit A samping
Standard area
Unit A samping 2 entries on this page Plastering work
Affan Awang
Plastering work Affan Unit A samping
Work by area Work area 08 Unit B tangga utama
Standard area
Unit B tangga utama 2 entries on this page Lantai Granit
Bais rizal
Lantai Granit Bais Unit B tangga utama
Work by area Work area 09 Unit C Room 14
Standard area
Unit C Room 14 2 entries on this page Work item needs review
Pawait Riswan
Work item needs review Pawait Unit C Room 14
Work by area Work area 10 Area not filled
Standard area
Area not filled 1 entry on this page Belanja / Logistik Site
Faisal
Belanja / Logistik Site Faisal Area not filled
Work by area Work area 11 Unit B belakang
Standard area
Unit B belakang 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Unit B belakang
Work by area Work area 12 Unit B Second Floor
Standard area
Unit B Second Floor 1 entry on this page Lantai Granit
Afis
Lantai Granit Afis Unit B Second Floor
Work by area Work area 13 Unit B tangga Room 17
Standard area
Unit B tangga Room 17 1 entry on this page Skim coat work
Gazali
Skim coat work Gazali Unit B tangga Room 17
Work by area Work area 14 Unit C Room 15
Standard area
Unit C Room 15 1 entry on this page Tile installation
Hanan
Tile installation Hanan Unit C Room 15
Work by area Work area 15 Unit C Room 22
Standard area
Unit C Room 22 1 entry on this page Work item needs review
Hoirul
Work item needs review Hoirul Unit C Room 22
Work by area Work area 16 Unit C Third Floor
Standard area
Unit C Third Floor 1 entry on this page Pembersihan Area Kerja
Dulbari
Pembersihan Area Kerja Dulbari Unit C Third Floor
Work by area Work area 17 Unit C ruangan GYM
Standard area
Unit C ruangan GYM 1 entry on this page Pembersihan Area Kerja
suarji
Pembersihan Area Kerja suarji Unit C ruangan GYM
Standard check and completeness Work item does not match standard naming yet 8 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 1 entry Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 1 entry The site input does not mention a work area, so it is not used as a final progress conclusion by area.