The day's site activity focused on Plastering work, Lantai Granit, and Skim coat work across 19 work areas, supported by Work item needs review, Pembersihan Area Kerja, and Pondasi.
Work by area
Work area 01Unit A facade
Standard area
Unit A facade
4 entries on this page
Plastering workSkim coat work
BambangHosnanMiskatYayan
Plastering workBambang
Unit A facade
Skim coat workHosnan
Unit A facade
Plastering workMiskat
Unit A facade
Plastering workYayan
Unit A facade
Work by area
Work area 02Unit A lobi
Standard area
Unit A lobi
4 entries on this page
Plastering workSkim coat work
JokoMujionoTopikZaeni
Skim coat workJoko
Unit A lobi
Work by area
Work area 03Unit B facade
Standard area
Unit B facade
4 entries on this page
Plastering workSkim coat work
AksehHalimNaimRopek
Plastering workAkseh
Unit B facade
Work by area
Work area 04Unit B Third Floor
Standard area
Unit B Third Floor
4 entries on this page
Lantai GranitPlastering work
AdipAfisDofirTormudi
Lantai GranitAdip
Unit B Third Floor
Work by area
Work area 05Unit B rooftop
Standard area
Unit B rooftop
4 entries on this page
Skim coat work
AlRidhoSolehWahyu
Skim coat workAl
Unit B rooftop
Work by area
Work area 06Unit A
Standard area
Unit A
3 entries on this page
Pembersihan Area KerjaWork item needs review
FattaSubawiWafi
Work item needs reviewFatta
Unit A
Work by area
Work area 07Unit A samping lobi
Standard area
Unit A samping lobi
3 entries on this page
Pondasi
AffanAwangFian
PondasiAffan
Unit A samping lobi
Work by area
Work area 08Unit B Second Floor
Standard area
Unit B Second Floor
3 entries on this page
Lantai GranitPlastering work
BaisDhonirizal
Lantai GranitBais
Unit B Second Floor
Work by area
Work area 09Unit B outdoor
Standard area
Unit B outdoor
2 entries on this page
Lantai Granit
MuhammadRiswan
Lantai GranitMuhammad
Unit B outdoor
Work by area
Work area 10Unit C basement
Standard area
Unit C basement
2 entries on this page
Work item needs review
HuriToni
Work item needs reviewHuri
Unit C basement
Work by area
Work area 11Unit C Room 12
Standard area
Unit C Room 12
2 entries on this page
Lantai Granit
AndriSam
Lantai GranitAndri
Unit C Room 12
Work by area
Work area 12Unit C Room 14
Standard area
Unit C Room 14
2 entries on this page
Work item needs review
ImronPawait
Work item needs reviewImron
Unit C Room 14
Work by area
Work area 13Area not filled
Standard area
Area not filled
1 entry on this page
Belanja / Logistik Site
Faisal
Belanja / Logistik SiteFaisal
Area not filled
Work by area
Work area 14Unit B
Standard area
Unit B
1 entry on this page
Work item needs review
Pak Farel
Work item needs reviewPak Farel
Unit B
Work by area
Work area 15Unit C Room 15
Standard area
Unit C Room 15
1 entry on this page
Tile installation
Hanan
Tile installationHanan
Unit C Room 15
Work by area
Work area 16Unit C Room 23
Standard area
Unit C Room 23
1 entry on this page
Work item needs review
Hoirul
Work item needs reviewHoirul
Unit C Room 23
Work by area
Work area 17Unit C Room 24
Standard area
Unit C Room 24
1 entry on this page
Skim coat work
Gazali
Skim coat workGazali
Unit C Room 24
Work by area
Work area 18Unit C kamar Third Floor
Standard area
Unit C kamar Third Floor
1 entry on this page
Pembersihan Area Kerja
suarji
Pembersihan Area Kerjasuarji
Unit C kamar Third Floor
Work by area
Work area 19Unit C ruangan GYM
Standard area
Unit C ruangan GYM
1 entry on this page
Pembersihan Area Kerja
Dulbari
Pembersihan Area KerjaDulbari
Unit C ruangan GYM
Standard check and completeness
Work item does not match standard naming yet8 entries
The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi1 entry
Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet1 entry
The site input does not mention a work area, so it is not used as a final progress conclusion by area.